FYI - Construction continues to move forward at East Elementary, with several important milestones completed this week.
Completed & In Progress
State boiler inspection – Passed
Underground plumbing inspection – Passed
Underground electrical inspection scheduled for September 14
Leveling plates being set in preparation for steel erection
Exterior metal panel trim and caulking continuing
Insulation work continues around the boilers and tunnel
Interior punch-list items continue to be addressed
Looking Ahead - Over the coming week, crews will continue work throughout the remaining construction areas, including:
Continued drywall work in the corridor construction area
Continued installation of exterior metal panels
Steel erection beginning September 12
Completion of interior punch-list items
Mechanical work on RTU2
Owner training on the new air handlers/fire alarm panel on September 17
First fire drill with students scheduled for Friday, September 18
We appreciate the continued hard work and coordination of our contractors, tradespeople, staff, and project partners as we move closer to completing the remaining portions of the East Elementary project.
Nate Sheridan - Site Supervisor