East Updates

FYI - Construction continues to move forward at East Elementary, with several important milestones completed this week.

Completed & In Progress

  • State boiler inspection – Passed

  • Underground plumbing inspection – Passed

  • Underground electrical inspection scheduled for September 14

  • Leveling plates being set in preparation for steel erection

  • Exterior metal panel trim and caulking continuing

  • Insulation work continues around the boilers and tunnel

  • Interior punch-list items continue to be addressed

Looking Ahead - Over the coming week, crews will continue work throughout the remaining construction areas, including:

  • Continued drywall work in the corridor construction area

  • Continued installation of exterior metal panels

  • Steel erection beginning September 12

  • Completion of interior punch-list items

  • Mechanical work on RTU2

  • Owner training on the new air handlers/fire alarm panel on September 17

  • First fire drill with students scheduled for Friday, September 18

We appreciate the continued hard work and coordination of our contractors, tradespeople, staff, and project partners as we move closer to completing the remaining portions of the East Elementary project.

Nate Sheridan - Site Supervisor